01 / Know the system

Start with the process. Then list the assets.

An OT inventory is useful when it connects a device to the process it supports, the person responsible for it and the consequences of losing it.

Updated · 2026-11-08

Define the boundary before collecting devices

Choose a plant, production line or clearly bounded service. Record what is inside the review and what depends on systems outside it. Include engineering workstations, controllers, human-machine interfaces, historians, network equipment and the interfaces used by suppliers. A device count alone does not explain how the operation works.

Begin with existing engineering drawings, maintenance records, configuration records and supplier documentation. Validate them with the people who operate the process. Treat discrepancies as work to resolve, rather than silently choosing whichever list looks newer. Discovery methods need an approved scope and an assessment of their operational impact.

A record that supports a decision

RecordQuestion it answersEvidence to retain
Process and locationWhat does this asset support?Approved system drawing or process description
Owner and maintainerWho can authorise a change?Named role and escalation route
Model, firmware, softwareDoes a vendor advisory apply?Verified version and collection date
Connections and dependenciesWhat happens if the link fails?Source, destination, purpose and approved route
Recovery and maintenanceCan we safely make and reverse a change?Restore procedure, test record and change window

Separate known, inferred and unknown

Keep the source and last validation date beside each record. An inferred operating system is different from a version checked by an authorised engineer. An unknown dependency should be visible to the reviewer, not replaced with a confident guess. Restrict access to inventory details: they may expose sensitive architecture.

Make the inventory part of maintenance

Assign ownership for updates after equipment replacement, supplier access changes, firmware work and commissioning. Review a sample against physical and configuration records. A spreadsheet with a date is not proof that a recovery procedure works; keep the recovery test as separate evidence.

Worked review

Illustrative example: a line controller appears in the asset register, but the engineering laptop used to restore its project does not. Add the dependency, identify the role that maintains the project file and agree how restoration can be tested without affecting production. The useful outcome is a verified dependency and an assigned action, not a higher inventory completeness score.

Continue with the remote-access review and the local review workbook.